Table 2 |
|
Cost of Condensate
P-Trap Maintenance, On-Demand – Typical
Conditions A. Labor Costs
. . . . . . . . . . . . . . . . . . . . . . . . . . . . per unit per yr. $25.00
1.
Clean or replace blocked traps –
bi-annually 2.
Replace freeze-damaged traps – one in
four annually 3.
Clean-up after trap blockage and
condensate flooding: · HVAC system –
floor and drain pan
·
Other affected property – supporting structure, roof and roof covering,
building floor, furniture, other equipment 4.
Clean-up after HVAC system start-up
(twice annually for schools), condensate geysering
(blowing) and flooding: · HVAC system –
floor, drain pan, fan, motor, inside
walls, ducts, etc. ·
Other affected property - supporting structure, roof and roof covering, building floor, furniture, other
equipment 5.
Travel time – Service and Supplies. ·
To and from service site and supply houses B. Service
Equipment and Supplies . . . . . . . . . . . . per unit per yr. $5.00
1.
Transportation Vehicle (mileage, etc.) 2.
Maintenance Tools 3.
Supplies – piping, fittings, biocides, etc. C. Surrounding Property Damage . . . . . . . .
. . . . . per
unit per yr. $20.00
1.
Supporting structure 2.
Roof covering 3.
Ceiling – tile, sheet rock, etc. 4.
Walls – wood, sheet rock, etc. 5.
Inside fixtures – desks, tables, etc. 6.
Books and supplies
7. Floor and floor coverings D. HVAC System Damage – Shortened Life . . .
. per unit
per yr. $30.00
1.
Deterioration of internal components – floor, drain pan, walls, fan,
fan motor, ducts,
control sensors, etc. E. Human Health* . . . . . . . . . . . . . . . . . . . . . . . . . . . per unit per
yr. +++?
1. HVAC
system contamination (internal): · Fungi, bacteria, and viruses 2.
Aerosol mist generated by geysering, caused
by entering high velocity air –
potential for spreading legionnella. Total estimated costs . . . . . . . . . . . . . . . . . . . . . . . per unit per yr. $80.00*Cost not
estimated, but may exceed all other cost. |